Question #274 Section 6
A new project has been set. Four main stakeholders besides the project manager and four other team members have been identified.
How many communication channels are available?
A. 8
B. 18
C. 36
D. 40
Answer: C
Reference:
https://www.izenbridge.com/blog/how-to-calculate-communication-channels/
Question #275 Section 6
A project conducts regular standup meetings to keep everyone updated on what each one of them is working on. What type communication is this?
A. Informal
B. Unofficial
C. Formal
D. Hierarchical
Answer: A
Reference:
https://yodiz.com/help/agile-scrum-meetings/
Question #276 Section 6
Which of the following are processes associated with Project Cost Management?
A. Develop Costs, Estimate Costs, Determine Budget, Control Costs
B. Develop Budget, Determine Budget, Determine Risks, Control Costs
C. Plan Cost Management, Estimate Costs, Determine Budget, Control Costs
D. Plan Budget Management, Determine Budget, Create Cost Accounts, Control Costs
Answer: C
Reference:
https://blog.masterofproject.com/cost-management/
Question #277 Section 6
A project manager called for a team meeting to estimate the project effort. During the session, the team went on to identify all the deliverables and analyzed the related
work. Each of the analyzed deliverables were estimated.
Which estimation method did the team use?
A. Rolling wave planning
B. Expert judgment
C. Decomposition
D. Data analysis
Answer: C
Question #278 Section 6
A project manager uses their networking skills to build agreement with a difficult stakeholder. What level of influence did the project manager apply?
A. Project level
B. Organizational level
C. Industry level
D. Influential level
Answer: C
Question #279 Section 6
A project had four phases, and at the end of the third phase, the project manager realized that some of the project execution steps could have been improved to avoid
team burn out
What should the project manager have done differently?
A. Conduct performance reviews
B. Review quality reports with the project team
C. Hold regular meetings with the project team
D. Conduct a retrospective session at the end of each phase
Answer: D
Question #280 Section 6
A project manager is in the process of working with stakeholders to meet their needs and expectations, and identifying and fostering communication and involvement.
Which process does this typically represent?
A. Monitor Stakeholder Engagement
B. Monitor Communications
C. Manage Communications
D. Manage Stakeholder Engagement
Answer: D
Reference:
https://www.memrise.com/course/352178/pmbok-5-project-management-exam-study/52/
Question #281 Section 6
Stakeholder identification and engagement should begin during what phrase of the project?
A. After the project management is completed
B. After the stakeholder engagement plan is completed
C. As soon as the project charter has been approved
D. After the communications management plan is completed
Answer: C
Reference:
https://pmstudycircle.com/2012/06/identify-stakeholders-project-management/
Question #282 Section 6
What type of risk is Variability risk?
A. Emerging risk
B. Non-event risk
C. Ambiguity risk
D. Integrated risk
Answer: D
Question #283 Section 6
A project manager is talking with their manager about the advantages of following a particular project management approach. What component of the project
manager's sphere of influence does this represent?
A. The project
B. The organization
C. Professional discipline
D. Across disciplines
Answer: C
Question #284 Section 6
What is the main benefit of the lessons learned register?
A. Provides validation requirements
B. Supplies monitoring and reporting methods
C. Improves the performance of future projects
D. Documents the status of deliverables and project results
Answer: C
Question #285 Section 6
What major skill sets comprise the PMI Talent Triangle?
A. Technical project management, technology management, and strategic and business management
B. Technical project management, leadership, and strategic and business management
C. Leadership, operational management, and technical project management
D. Organizational management, operational management, and technology management
Answer: B
Reference:
https://www.pmi.org/learning/training-development/talent-triangle#:~:text=The%20ideal%20skill%20set%20%E2%80%94%20the,%E2%80%94%
20and%20now%2C%20digital%20skills
.
Question #286 Section 6
What tool or technique will establish expected behaviors for project team members?
A. Ground rules
B. Decision making
C. Power/influence grid
D. Stakeholder engagement assessment matrix
Answer: A

User: Meera*****

Thanks to killexams.com, I was able to pass the challenging capm exam, which I would not have been able to do on my own. The questions were easy to memorize, and I appreciated that they were real and accurate, which helped me feel more confident going into the exam. With my certification in hand, I can now proudly add it to my resume.
User: Rhodie*****

I became CAPM certified last week, and this professional path is very exciting. If you are still considering it, make sure you get questions and answers to prepare for the CAPM exam. Its a massive time saver, and you get precisely what you need to know for the CAPM exam. Thats why I selected it, and I never looked back.
User: Ibrahim*****

When I searched for a great practice test for this precise topic online, I could not find one that perfectly explained the essential matters. However, when I discovered killexams.com brain dump practice test material, I was truly surprised by how well it covered everything I needed. I am grateful for this material and used it for my schooling.
User: Levushka*****

I am thrilled to announce that I passed the CAPM exam with flying colors thanks to the assistance of killexams.com questions and answers. The materials provided were invaluable, and I found them to be very useful. Not only did they help me pass the exam, but I am confident that anyone can achieve the same results after using their CAPM practice tests training. The explanations were particularly helpful, and the overall experience was enjoyable.
User: Charlie*****

Killexams.com is an amazing product that is both user-friendly and easy to use. It has motivated me in many ways, and I am grateful for their support. When I was studying for the IT CERTIFIED ASSOCIATE IN PROJECT MANAGEMENT (CAPM) - 2024 exam, I found it challenging to comprehend the complex topics. However, once I discovered Killexams.com, I was able to overcome my difficulties and pass the exam with ease.

Features of iPass4sure CAPM Exam

  • Files: PDF / Test Engine
  • Premium Access
  • Online Test Engine
  • Instant download Access
  • Comprehensive Q&A
  • Success Rate
  • Real Questions
  • Updated Regularly
  • Portable Files
  • Unlimited Download
  • 100% Secured
  • Confidentiality: 100%
  • Success Guarantee: 100%
  • Any Hidden Cost: $0.00
  • Auto Recharge: No
  • Updates Intimation: by Email
  • Technical Support: Free
  • PDF Compatibility: Windows, Android, iOS, Linux
  • Test Engine Compatibility: Mac / Windows / Android / iOS / Linux

Premium PDF with 1102 Q&A

Get Full Version

All PMI Exams

PMI Exams

Certification and Entry Test Exams

Complete exam list