Question: 20
Within the SAFE principles (10), what is related to this principle: #3, "Assume variability; preserve options,"?
A. Stronger Definition of Done
B. Specification traceability
C. Better economic results
D. Up front design of systems
Answer: C
Explanation:
Solution development is an inherently uncertain process. Technical variability and market variability are present
throughout the development process. Innovative new systems have, by definition, never been developed before, so
there is no guaranteed path to success. If there were, it wouldnât be innovation. Thatâs why we love this business. To
assure forward progress, system developers are inclined to reduce variability as quickly as possible. The more
deterministic things are, the better we feel. Thatâs just human nature. It seems that the more we think we know and
have already decided, the further along we think we are. And thatâs true up to a point, but even then variability is a
constant presence. Variability is inherently neither bad or goodâit just is what it is. But itâs the economics associated
with the timing and type of variability that determines outcomes. The goal is to manage variability, and to preserve
options, providing the controls and flexibility teams need to build great solutions.
Question: 21
The product backlog contains 60 story points. The team velocity is around 20 story points per iteration.
How many Iterations would it take to finish the backlog?
A. 1 Iteration
B. 2 Iterations
C. 4 Iterations
D. 3 Iterations
Answer: D
Explanation:
60/20 = 3
Question: 22
When is Continuous Exploration happening?
A. On demand, based on market rhythms and events
B. Every Iteration
C. During the IP Iteration in preparation for PI Planning
D. In the first PI Iteration to prepare for work in Iteration 2 and deployment in Iteration 3
Answer: B
Explanation:
Continuous Exploration (CE) is the process that drives innovation and fosters alignment on what should be built by
continually exploring market and customer needs, and defining a Vision, Roadmap, and set of Features for a Solution
that addresses those needs.
Question: 23
Who is facilitating the Scrum of Scrums?
A. Business Owners
B. Scrum Master
C. Product Owner
D. Release Train Engineer
Answer: D
Explanation:
The Release Train Engineer (RTE) typically facilitates a weekly (or more frequently, as needed) Scrum of Scrums
(SoS) event. The SoS helps coordinate the dependencies of the ARTs and provides visibility into progress and
impediments. The RTE, representatives from each team (often the Scrum Master), and others (where appropriate) meet
to review their progress toward milestones and PI objectives, and dependencies among the teams. The event is
timeboxed for 30-60 minutes and is followed by a âmeet afterâ where individuals who want to do a deeper dive into
specific problems can remain behind.
Question: 24
What are the three inputs to start PI Planning?
A. A set of PI Objectives
B. Product/Solution Vision
C. Business context
D. Solution Roadmap
E. Top-10 Features
F. Ready user stories
Answer: A,B,C,E
Explanation:
Program Increment (PI) Planning is a cadence-based, face-to-face event that serves as the heartbeat of the Agile
Release Train (ART), aligning all the teams on the ART to a shared mission and Vision. PI planning is essential to
SAFe: If you are not doing it, you are not doing SAFe. Inputs to PI planning include: Business context (see âcontent
readinessâ below) Roadmap and vision Top 10 Features of the Program Backlog A successful PI planning event
delivers two primary outputs: Committed PI objectives C A set of SMART objectives that are created by each team
with the business value assigned by the Business Owners. Program board C Highlighting the new feature delivery
dates, feature dependencies among teams and relevant Milestones.
Question: 25
How feedback is connected with optimum batch size?
A. Feedback and batch size are generally not connected
B. Small batch sizes enable faster feedback with lower transaction costs
C. Large batches reduce transaction cost and provide a higher return on investment
D. Lack of feedback contributes to higher holding cost
Answer: B
Explanation:
The economically optimal batch size depends on both the holding cost (the cost for delayed feedback, inventory decay,
and delayed value delivery) and the transaction cost (the cost of preparing and implementing the batch). To improve
the economics of handling smaller batchesâand thus increase throughputâteams must focus on reducing the transaction
costs of any batch. This typically involves increasing the attention to and investment in infrastructure and automation,
including things such as continuous integration, automating the build environment, automated regression testing and
more. (This is a primary purpose of implementing DevOps.)
Question: 26
What is defining the best the Program Vision?
A. It provides an outline of the Features for the next three Program Increments
B. It summarizes the team PI Objectives for the current Program Increment
C. It drives the allocation of budget for the Agile Release Train
D. It expresses the strategic intent of the Program
Answer: D
Explanation:
When using Full SAFe or Large Solution SAFe, each ART will likely have its own vision, detailing the direction of
the specific capabilities or subsystems that it produces. This vision should be tightly coupled to the solution vision it
supports.
Question: 27
What kind of items is describing behaviors in the Large Solution view?
A. Capabilities
B. User Stories
C. Features
D. Benefits
Answer: A
Explanation:
Large Solution SAFe describes additional roles, practices, and guidance to build and evolve the worldâs largest
applications, networks, and cyber-physical systems. Large Solution SAFe (Figure 1) configuration includes the
following constructs: The Essential SAFe configuration An additional competency, Enterprise Solution Delivery that
describes how to apply Lean-Agile principles and practices to the specification, development, deployment, operation,
and evolution of the worldâs largest and most sophisticated software applications, networks, and cyber-physical
systems. The large solution level roles, artifacts, and events. The full spanning palette A connection to the Enterprise
or Government entity the solution supports The following Large Solution SAFe artifacts help coordinate multiple
ARTs and suppliers: Capabilities C Capabilities are a higher-level solution behavior that typically spans multiple
ARTs. They are sized and split into multiple features so that they can be implemented in a single PI. Enabler
CapabilitiesC Enabler capabilities support the activities needed to extend the Architectural Runway to provide future
business functionality and include exploration, architecture, infrastructure, and compliance. Solution Epics C Solution
Epics are epics implemented by a single Solution Train. Nonfunctional Requirements (NFRs) C NFRs define system
attributes such as security, reliability, performance, maintainability, scalability, and usability. These are incorporated in
solution intent. Solution Backlog C Solution Backlog is the holding area for upcoming capabilities and enablers, each
of which can span multiple ARTs and are intended to advance the solution and build its architectural runway.
Question: 28
What are the three pillars of Scrum: transparency, inspection ...?
A. Adaptation
B. Collaboration
C. Self-organization
D. Respect
Answer: A
Explanation:
Scrum pillars are Transparency, Inspection and Adaptation.
Question: 29
What is SAFE?
A. SAFE is a framework to implement Devops
B. SAFE is based of proven, integrated Lean practices and principles, Agile and Devops
C. SAFE is a tool for budget management
Answer: B
Explanation:
Scaled Agile Framework® (SAFe®) empowers complex organizations to achieve the benefits of Lean-Agile
software and systems development at scale. SAFe is the worldâs leading framework for scaling Agile across the
enterprise. Used by hundreds of the worldâs largest organizations, SAFe sustains and drives faster time-to-market,
dramatic increases in productivity and quality, and improvement in employee engagement. SAFe is designed to help
businesses continuously and more efficiently deliver value on a regular and predictable schedule. It provides a
knowledge base of proven, integrated principles and practices to support enterprise agility.
Question: 30
What is the foundation of the customer-centric?
A. Market and user research
B. Product lifecycle
C. Customer value
D. Whole product solution
Answer: A
Explanation:
The foundation of the customer-centric enterprise is market and user research that creates actionable insights into the
problems customers face, the solution requirements, and the solution context. Market research tends to drive strategy;
user research tends to drive design. Research activities occur continuously and are directly supported through
Continuous Exploration in the Continuous Delivery Pipeline, product telemetry data, and the feedback loops that exist
between the solution and the Solution Context.
User: Eugene***** I was able to achieve higher scores in my safe-agilist certification with the help of affordable products. I purchased the safe-agilist exam engine to make it easier for me to meet the rigorous standards of this certification. Additionally, I bought the safe-agilist exam brain dump to ensure outstanding grades within the certification. These products proved to be the best choice because they were designed according to my mindset. Within 15 days, I was able to prepare and score exceptionally well with the help of these practical products. I am writing to express my gratitude to all of you for your great services. |
User: Yaroslav***** To prepare for my safe-agilist exam and achieve high scores, I used killexams.com safe-agilist practice tests and exam simulator. Thanks to this excellent resource, I passed the exam. I highly recommend this package to everyone planning to take the safe-agilist exam. |
User: Lilya***** I owe a debt of gratitude to Killexams.com for providing such high-quality exam practice tests. The SAFE-AGILIST exam practice tests were valid and helped me achieve a 95% score. I plan to return for additional test prep and highly recommend Killexams.com to anyone looking for comprehensive study materials. |
User: Lenaya***** When I heard that Killexams.com had updated their safe-agilist brain practice test, I immediately purchased it. Their exam practice test was comprehensive and included all the new areas, making the exam seem more manageable. Their prompt response time and helpful customer support are highly commendable. |
User: Stassia***** The accurate questions and answers provided by Killexams.com helped me pass safe-agilist on the first try with 78% marks. My actual score was 90%, but due to poor marking, it came down to 78%. I appreciate the excellent job done by the Killexams.com team and wish them all the success. |
Features of iPass4sure SAFe-Agilist Exam
- Files: PDF / Test Engine
- Premium Access
- Online Test Engine
- Instant download Access
- Comprehensive Q&A
- Success Rate
- Real Questions
- Updated Regularly
- Portable Files
- Unlimited Download
- 100% Secured
- Confidentiality: 100%
- Success Guarantee: 100%
- Any Hidden Cost: $0.00
- Auto Recharge: No
- Updates Intimation: by Email
- Technical Support: Free
- PDF Compatibility: Windows, Android, iOS, Linux
- Test Engine Compatibility: Mac / Windows / Android / iOS / Linux
Premium PDF with 126 Q&A
Get Full VersionAll SAFe Exams
SAFe ExamsCertification and Entry Test Exams
Complete exam list