Certification Practice Test | PDF Questions | Actual Questions | Test Engine | Pass4Sure
Scrum-PSM-II : Professional Scrum Master II Exam
Scrum Scrum-PSM-II Questions & Answers
Full Version: 180 Q&A
Scrum-PSM-II Dumps
Scrum-PSM-II Braindumps
Scrum-PSM-II Real Questions
Scrum-PSM-II Practice Test
Scrum-PSM-II Actual Questions
Scrum
Scrum-PSM-II
Professional Scrum Master II
https://killexams.com/pass4sure/exam-detail/Scrum-PSM-II
Question: 170
According to the values of Scrum, which is the best way to create Development Teams?
A. The Product Owner will create a skills matrix according to what is needed for the project and work with
the technical leads to allocate resources to the team.
B. Work with the leadership team to allocate members according to skills, seniority and experience to ensure
that all Development Teams are balanced fairly.
C. Provide boundaries to the developers and allow them to self-organize into Development Teams.
Answer: C
Explanation:
When the values of commitment, courage, focus, openness and respect are embodied and lived by the Scrum Team,
the Scrum pillars of transparency, inspection, and adaptation come to life and build trust for everyone and self-
organizing teams will be enabled to choose how best to accomplish their work.
Question: 171
A Development Team has a total of six members, 4 members who work full time in the office and 2 members who
work part time at home. The Development Team is complaining that it is too difficult to synchronize every day and
has suggested having the Daily Scrum every other day instead.
What would be three key concerns if the Daily Scrum is held less frequently? (Choose three.)
A. Impediments are raised and resolved more slowly.
B. Opportunities to inspect and adapt the Sprint Backlog are reduced.
C. Less information about the progress will be shared causing the Sprint plan to become inaccurate and
reducing transparency over progress toward the Sprint Goal.
D. The Scrum Master loses the ability to update the burndown chart adequately.
E. The Product Owner cannot accurately inspect utilization of the individual team members.
Answer: ABC
Explanation:
The Daily Scrum is an internal meeting for the Development Team to inspect progress toward the Sprint Goal and
to inspect how progress is trending toward completing the work in the Sprint Backlog. The Daily Scrum optimizes
the probability that the Development Team will meet the Sprint Goal. Every day, the Development Team should
understand how it intends to work together as a self-organizing team to accomplish the Sprint Goal and create the
anticipated Increment by the end of the Sprint.
Reducing the frequency of the event will increase the length of the feedback loop and adds risk if the team deviates
too far off course.
Question: 172
Steven is a Scrum Master asked to assist in creating five new Scrum Teams that will be working to build a highly
anticipated product. He talks with them about the importance of being able to integrate their Increments by the end
of their Sprints. This includes the first Sprints. The product is very important to both the end users and the
organization.
Of the choices raised by future team members, what would Steven encourage?
A. Each Scrum Team delivers Increments in its own code branch. After UAT is performed at the Sprint
Review, the code branch is isolated until enough Increments are considered acceptable. All code branches
will then be merged duringthe release phase.
B. Each Scrum Team delivers functionality at the end of each Sprint. New Product Backlog items will then
be added to the next Sprint Backlog to integrate their functionality with the other teams to create a unified
Increment.
C. All Scrum Teams agree on a mutual understanding of ‘done’ that defines all work necessary to deliver a
potentially shippable Increment that includes all previous Increments delivered for the product.
D. Wait until enough of the infrastructure and architecture is in place before starting the first Sprints. This
will increase the success of delivering integrated Increments in Sprint 1.
Answer: C
Explanation:
When a Product Backlog item or an Increment is described as "Done", everyone must understand what "Done"
means. If there are multiple Scrum Teams working on the system or product release, the Development Teams on all
the Scrum Teams must mutually define the definition of "Done" to have a shared understanding of what it means
for work to be complete, to ensure transparency. Each Increment is additive to all prior Increments and thoroughly
tested, ensuring that all Increments work together.
Question: 173
Three Development Teams are currently building a single product and pulling work from the same Product
Backlog. All three teams have identified that they will need Dan, a database specialist, to work full time in their
team for the next several Sprints.
What should Steven, the Scrum Master, do to solve this potential problem?
A. Manage the items in the Sprint Backlogs so that Dan can be utilized evenly for each team.
B. Assign Dan to the team with the most urgent tasks first and then move him to the next team and so on
until the required support is completed.
C. Facilitate a discussion with all Development Teams on how they want to deal with this issue, and help
them implement their preferred solution.
D. Ask Dan to work with the HR department to recruit and hire additional database specialists. In the
meantime, have the Product Owner move items that do not depend on Dan to the top of the Product
Backlog.
Answer: C
Explanation:
As a servant/leader, the Scrum Master facilitates conversations through open ended questions in order to help the
team members make the best possible decisions according to what is known at the time. He/she does not approve
or reject team decisions but ensures the team stays within the boundaries of the Scrum framework.
Question: 174
An organization wants to apply Scrum to build a new product and has hired Steven to be the Scrum Master of three
new teams that will build the first release. The organization is new to Scrum and asks Steven for advice on how to
start. Which two things should Steven first advise? (Choose two.)
A. Each Scrum Team has its own Product Backlog with items only their team will be working on.
B. One Product Backlog to represent all of the known work needed to be done for the product.
C. Three Product Owners, one for each Scrum Team.
D. Having one Product Owner to be accountable for maximizing the flow of value throughout the
development process and provide transparency on the overall progress.
Answer: BD
Explanation:
The Scrum Master serves the organization in several ways, including: Leading and coaching the organization in its
Scrum adoption; Planning Scrum implementations within the organization; Helping employees and stakeholders
understand and enact Scrum and empirical product development.
Question: 175
Steven, the Scrum Master, is approached by one of the Development Team members saying that they are not
completing regression tests for all of the work they are performing to the level defined in the Definition of Done.
They have discussed this with the Product Owner and decided to remove regression testing from the Definition of
Done.
Which two actions are the most appropriate for Steven to take? (Choose two.)
A. Reject the decision as the long term maintainability of the product will be negatively impacted by
modifying the Definition of Done.
B. Accept the decision as a mutual agreement has been made between the Development Team and the
Product Owner.
C. Ask the Development Team and the Product Owner what problem they are trying to solve by altering the
Definition of Done and removing regression testing from it. In what ways will this decision impact
transparency and quality?
D. Ask the Development Team and the Product Owner if they are still able to produce potentially shippable
product increments by altering the Definition of Done?
Answer: CD
Explanation:
As a servant/leader, the Scrum Master facilitates conversations through open ended questions in order to help the
team members make the best possible decisions according to what is known at the time. He/she does not approve
or reject team decisions but ensures the team stays within the boundaries of the Scrum framework.
Question: 176
At the end of the eighth Sprint, the internal sponsors are upset and angry with the progress of the product being
built. The current state of the product is not as expected and will require additional Sprints and more budget than
originally anticipated at the start of the project.
What factors may have led to this? (Choose three.)
A. The Product Owner has not been engaging with sponsors frequently enough and has not been kept aware
of the overall progress of the project.
B. The sponsors haven’t been using the Sprint Reviews to actively engage, and inspect and evaluate progress.
C. The scope changes have not been tracked adequately and the change request process has not been
followed properly.
D. The stakeholders have not been using the Daily Scrum effectively to track the Development Team’s
progress.
E. The Scrum Master has not ensured transparency.
F. The project plan proposed to the sponsors at the start of the project followed stringently.
Answer: ABE
Explanation:
One of the principles of agility includes working closely with business people. In order to manage stakeholder
expectation, there must be open communication (through collaboration and transparency) throughout the project
cycle. This maximizes alignment, helps with making business decisions, and reduces risk.
Although, the Scrum Guide does not directly state that the Scrum Master is responsible for ensuring transparency it
is implicit. The Scrum Master is responsible for the process in which Scrum is adopted and enacted. Scrum is
founded on empiricism and the Scrum Master helps those inside and outside the team work in an empirical
environment which includes transparency (one of the three pillars of empiricism).
Question: 177
Paul is a Product Owner for multiple products. Each product is allocated a dedicated Scrum Team and a set budget.
Based on the average velocity of a previous product release, Paul had estimated a new product to take 9 Sprints to
complete. The average velocity of the previous product release was 50 completed units of work per Sprint. Over the
first 3 Sprints, the Development Team reported an average velocity of 40 completed units per Sprint, while not
fully completing the required integration tests. The Development Team estimates that integration testing would
require additional effort to make the increments shippable. The Development Team is unsure if the required
velocity is achievable.
What is the most effective way to recover?
A. In the next Sprints, the Development Team strives to make the selected work as close to ‘done’ as
possible and at the minimum 90% completed. Any undone work is divided into new Product Backlog Items
that will be deferred to the lastSprint in order to maintain stable velocity.
B. The Development Team informs Paul that the progress he has perceived to date is not correct. The
Increment is not releasable. They give Paul their estimate of the effort it would take to get the previous work
‘done’, and suggest doingthat work first before proceeding with new features. The team also re-estimates the
effort to make the remaining Product Backlog items ‘done’, including all integration effort. In the end, it is
Paul’s call to continue the project or to cancel.
C. The Scrum Master will manage the Sprint Backlog and assign work to the Development Team members
to ensure maximum utilization of each member. He/she will keep track of unused resources so that it does
not impact the budget.Unused budget can be allocated for additional Sprints if needed.
D. The Scrum Master sets the open work aside to be performed in one or more release Sprints. They remind
Paul to find funding for enough Release Sprints in which this remaining work can be done. Up to one release
Sprint per threedevelopment Sprints may be required. It is Paul’s role to inform users and stakeholders of
the impact on the release date.
Answer: B
Explanation:
Scrum is founded on empirical process control and asserts that knowledge comes from experience and making
decisions based on what is known. Scrum employs an iterative, incremental approach to optimize predictability and
control risk. At the end of every Sprint, an increment of ‘done’ work must be available in order to inspect and
adapt accordingly.
Question: 178
Paul, a Product Owner of one of the Scrum Teams, has been attending the Daily Scrum. During the Daily Scrum,
the Development Team members have been reporting their daily work to Paul so that he is aware of their Sprint
progress and what each member is working on.
What is the best action for the Scrum Master to take?
A. Ask Paul to stop attending the Daily Scrum.
B. Coach Paul and Development Team members on the purpose of the Scrum events and let them figure out
what to do in this situation.
C. Allow the Paul to participate in the Daily Scrum as he is responsible for the success of the product.
D. Facilitate the Daily Scrums to avoid any conflicts between the Development Team members and Paul.
Answer: B
Explanation:
Because the Development Team is the ones doing the work, they are best suited to inspect and adapt the progress
toward the Sprint Goal. At minimum, this is done every 24 hours through the Daily Scrum. It is the Scrum Master’s
responsibility to teach the Scrum Team the value and objective of each Scrum event in order for them to optimize
the benefits of each event. Because the Daily Scrum is owned by the Development Team, it is up to them on how
they should run it but the Scrum Master can provide guidance to ensure it adheres to the Scrum guidelines.
Question: 179
A Scrum Master is not only a servant-leader to the Scrum Team and organization, it’s also considered a
management position.
Which three activities describe what a Scrum Master manages as reflected by the Scrum Guide? (Choose three.)
A. Reporting on the performance of the Sprint.
B. The way Scrum is understood and enacted within the organization.
C. Managing the capacity and utilization of each Development Team member.
D. Managing the process in which Scrum is applied.
E. Managing the Product Backlog items and work in the Sprint Backlog.
F. Removing organizational impediments that limits the team’s progress and productivity.
Answer: BDF
Explanation:
The Scrum Master must understand the principles and values behind agility as well as the Scrum theory. He/she
also must act in ways that reflects the values of Scrum and creates an environment for others to also embrace those
values. He/she is responsible for ensuring the team’s process stays within the boundaries of the Scrum framework
as well as helping and supporting the team with continuous improvement.
Question: 180
An organization has just hired you as a new Scrum Master to help them transition their teams from their current
traditional process to Scrum. The teams are currently structured to specialize in a single function. This is also
known as component teams where a team would only address a single layer (i.e. design, frontend, backend,
database, testing, etc.). You’ve introduced the concept of cross-functional teams where all the skills needed to
produce business functionality, from end to end, are inside of a single team.
What should you keep in mind when transitioning from siloed teams to cross-functional teams? (Choose two.)
A. It is easier to compare the performance between cross-functional teams in order to identify to which
teams to assign tasks and which teams need additional coaching.
B. Newly formed teams will need time to stabilize before reaching their peak performance. During the initial
stages of forming, performance will suffer and productivity may be low, although even then delivery of
business value is still likelyto increase.
C. Without feature teams, you cannot do Scrum. Postpone Scrum adoption until the teams are reorganized
in feature teams.
D. People from the different layers and components will need time to become accustomed to working and
delivering unified functionality together as one Scrum Team thus productivity may suffer.
Answer: BD
Explanation:
Forming a team takes time, and members often go through recognizable stages as they change from being a
collection of strangers to a united group with common goals. Bruce Tuckman’s Forming, Storming, Norming, and
Performing model describes these stages. When you understand it, you can help your new team become effective
more quickly.
User: Verochka***** I scored 92% in my SCRUM-PSM-II certification thanks to the excellent products offered by killexams.com. Technical concepts and difficult language in my certification were challenging to understand, but killexams.com made it easy for me. This platform made my job easy, and I am grateful for my success. |
User: Pat***** When I could not find any study materials for the SCRUM-PSM-II exam, I purchased killexams.com, and it turned out to be better than any book because it provides real exam questions. I highly recommend it to anyone planning to take the SCRUM-PSM-II exam. |
User: Nessa***** I am thrilled to share that I passed the SCRUM-PSM-II exam today with a score of 100% using killexams.com as my study resource. This was an unexpected accomplishment, but I am grateful for the comprehensive coverage of all topics and the abundance of questions provided by killexams.com. It was a pleasant surprise to see the same questions in the actual exam, and I highly recommend using this resource to others. |
User: Krugan***** Killexams is the best IT exam preparation program I have ever come across. My scrum-psm-ii exam is in a few days, and I feel well-equipped and reassured, especially now that I have read all the great reviews here. The exam simulator is very helpful, and it is easy to remember the questions and answers. Also, going through them repeatedly helps to see a bigger picture and understand the concepts better. So far, I have had a great experience with Killexams. |
User: Yury***** When I was taking an IT course on scrum-psm-ii, I struggled with finding a guide to help me. However, I discovered a website that was very popular in the market - Killexams.com. Their practice questions and materials helped me prepare for the exam, and I was able to secure top marks. I am grateful to Killexams.com for helping me overcome my laziness and achieve success. |
Features of iPass4sure Scrum-PSM-II Exam
- Files: PDF / Test Engine
- Premium Access
- Online Test Engine
- Instant download Access
- Comprehensive Q&A
- Success Rate
- Real Questions
- Updated Regularly
- Portable Files
- Unlimited Download
- 100% Secured
- Confidentiality: 100%
- Success Guarantee: 100%
- Any Hidden Cost: $0.00
- Auto Recharge: No
- Updates Intimation: by Email
- Technical Support: Free
- PDF Compatibility: Windows, Android, iOS, Linux
- Test Engine Compatibility: Mac / Windows / Android / iOS / Linux
Premium PDF with 180 Q&A
Get Full VersionAll Scrum Exams
Scrum ExamsCertification and Entry Test Exams
Complete exam list