Certification Practice Test | PDF Questions | Actual Questions | Test Engine | Pass4Sure
PMI-RMP : PMI Risk Management Professional Exam

PMI PMI-RMP Questions & Answers
Full Version: 443 Q&A
Latest PMI-RMP Practice Tests with Actual Questions
Get Complete pool of questions with Premium PDF and Test Engine
Exam Code : PMI-RMP
Exam Name : PMI Risk Management Professional
Vendor Name :
"PMI"
PMI-RMP Dumps
PMI-RMP Braindumps PMI-RMP Real Questions PMI-RMP Practice Test
PMI-RMP Actual Questions
PMI
PMI-RMP
PMI Risk Management Professional
https://killexams.com/pass4sure/exam-detail/PMI-RMP
Question #428
In what way can the risk manager determine when poor risk planning techniques are influencing the scope, schedule, quality, and/or budget of the project?
Evaluate the results of the Monte Carlo analysis.
Document and periodically update project risk information
Monitor project metrics and performance information.
Update the risk management plan.
Answer: C Question #429
How can the project manager rank competing stakeholder priorities for all the identified risks?
Perform qualitative and quantitative risk analysis.
Engage the project sponsor to decide.
Refer to stakeholder analysis prioritization tree.
Perform a review of organizational process assets.
Answer: A Question #430
A project team is conducting initial risk planning. What other risk-related task should the project manager perform?
Identifying the risk threshold
Determining the risk register headings
Scoring the risks utilizing the risk matrix
Prioritizing the risks in the risk register
Answer: A Question #431
What are the critical success factors for the Plan Risk Management process?
Mitigate all risks, engage stakeholders, and follow organizational policies.
Identify and address barriers, engage stakeholders, and follow organizational policies.
Contingency reserves engage stakeholders and follow organizational policies.
Identify and address barriers, engage stakeholders, and follow government regulations.
Answer: B Question #432
A project team's risk facilitator identifies a number of risks and must prioritize them based on the organization's risk appetite levels. Which technique should be used?
PERT
Stakeholder risk profile analysis
Project scope statement analysis
Monte Carlo technique
Answer: B Question #433
A risk manager wants to determine which risks are going to have the highest impact on a project. Which of the following techniques should the risk manager use?
Assumptions analysis
Sensitivity analysis
Root cause analysis
Prioritization matrices
Answer: D Question #434
The project manager wants risk metrics established for the new project. Which of the following metrics listed is best suited for this purpose?
Effectiveness of the work breakdown structure
Number of approved project change requests
Number of detects identified
Effectiveness of response plans
Answer: D Question #435
Which of the following would a proactive risk manager do during the Monitoring and Controlling Process?
Develop risk responses, create risk management plan, and stay alert for risk events.
Update the lessons learned documents, develop risk responses, and create the risk management plan.
Review identified risks, stay alert for risk events, and remind team members to keep the risk manager informed about risk triggers.
Review lessons learned document to identify risks, quantity risks, and lower impact ratings.
Answer: C Question #436
A cost analyst team member asks the project manager for the latest risk data for inclusion with the cost estimates for the project. Which tool should the cost analyst team member use to identify the probability of achieving specific cost targets?
Monte Carlo analysis
Decision tree analysis
Analogous estimating
Brainstorming
Answer: A Question #437
Most risks are assessed for probability and impact. Which of the following are other factors that should be considered?
Urgency and complexity
Manageability and cost
Urgency and manageability
Manageability and complexity
Answer: C Question #438
A pharmaceutical company undertakes a new, year-long research and development (R&D) project. The company pursues high margins on investments and an aggressive growth strategy. They maintain a central program management office (PMO) to assist with new projects and record data on past project performance.
The company leadership regularly makes decisions regarding the full suite of company projects and requires comparative data and reports. Project leadership is well-versed in risk management and the PMO requires full documentation of project management artifacts.
Based on the characteristics of this new project, which of the following best describes the risk strategy for the project?
Low stakeholder risk appetite, leverage historical project planning data, develop standard metrics and reports, and develop a formal risk management plan.
High stakeholder risk appetite; leverage historical project planning data, develop standard metrics and reports, develop a formal risk management plan.
High stakeholder risk appetite; leverage historical project planning data, utilize informal metrics and reports, develop risk management training.
Low stakeholder risk appetite; collect new project data, create custom metrics and reports, and develop a formal risk management plan.
Answer: B Question #439
Which of the following should the risk manager consider as external environmental factors when creating the risk management plan?
Government regulations, industry best practice templates, organizational standard processes, and competitor landscape
Government regulations, industry standards, conditions of the marketplace, and competitor landscape
Government regulations, risk categories, organizational standard processes, and competitor landscape
Government regulations, human resource policies and procedures, organizational standard processes, and competitor landscape
Answer: B Question #440
A project manager is leading a project review meeting with the risk manager and the other project stakeholders. Which of the following are typical risk-related agenda items for a project review meeting?
Enterprise environmental factors and the risk register
Risks closed in the last period and the risk appetite of the organization
Organizational process assets and the risk register
Risks closed in the last period and the trigger conditions that have occurred
Answer: D Question #441
As part of identifying the risk appetite of project stakeholders, the project manager must first identify the stakeholders. Which of the following inputs are used to identify project stakeholders?
Project charter, management reserve, enterprise environmental factors, and organizational process assets
Project management plan, human resource plan, enterprise environmental factors, and organizational process assets
Project charter, bid documents, enterprise environmental factors, and organizational process assets
Project charter, communications management plan, enterprise environmental factors, and organizational process assets
Answer: C Question #442
The project manager receives an updated project schedule from a sub team detailing the deliverables, dates, and durations for a critical milestone on the development and testing for offshore activities. This report is received one hour before a meeting with the chief executive officer (CEO) to present an updated master schedule of the critical path. The CEO has been promised a discussion on the project schedule several times. However, based on the recent update from the off-shore team, the project manager realizes this new schedule is not realistic. There are new risks associated with it and it is not well thought out. Some key stakeholders want to present this revised plan to the CEO. This meeting has been postponed twice already.
Which action should the project manager take before meeting with the CEO?
Talk to the stakeholders before the meeting to discuss the options and ask their opinion.
Present the revised master schedule to the CEO with the caveat that its being updated as new information is received, and these are the current dates at this point.
Request the meeting be re-scheduled before presenting the master schedule to the CEO, stating that new major risks were identified and need to be assessed thoroughly.
Present the revised schedule to the CEO and only answer questions about validity, if asked.
Answer: A Question #443
Which of the following are examples of relevant data gathering tools?
Risk response plan and interviews
Questionnaires and historical data
Work breakdown structure an historical data
Work breakdown structure and interviews
Answer: B
User: Puskin*****![]() ![]() ![]() ![]() ![]() I mostly used a mix of books to prepare for the exam. The questions in the Killexams.com material matched the exam questions accurately, which was incredibly helpful. I passed the exam with 89% marks about a month ago. Whoever tells you that pmi-rmp is too hard, do not believe them. The exam is tough, but using Killexams.com Questions and Answers and exam simulator as my sole source of preparation was the key to my success. |
User: Jacob*****![]() ![]() ![]() ![]() ![]() Before joining killexams.com, I attempted the pmi-rmp practice questions more than once but was unsuccessful in my studies. I did not realize where I lacked in getting fulfillment until I became a member of killexams.com, which provided the missing piece of pmi-rmp practice material. Preparing for pmi-rmp with pmi-rmp sample questions is highly convincing, and the pmi-rmp practice books designed by killexams.com are excellent. |
User: Regina*****![]() ![]() ![]() ![]() ![]() As an authority on the subject, I knew I needed help from practice tests if I wanted to pass a challenging exam like PMI RISK MANAGEMENT PROFESSIONAL. I was correct. The Killexams.com practice tests have an interesting technique that makes difficult subjects easy. They manage them in a quick, clean, and precise manner, making it easy to remember and recall the information. I did so and was able to answer all of the questions in half the time. Truly, Killexams.com practice tests are the right companion in need. |
User: Stesha*****![]() ![]() ![]() ![]() ![]() Passing the pmi-rmp exam was incredibly tough for me, but Killexams.com helped me gain composure and prepare with their pmi-rmp practice tests. The pmi-rmp exam simulator was very useful, and I was able to pass the exam and get promoted in my company. |
User: Saasha*****![]() ![]() ![]() ![]() ![]() In conclusion, Killexams.com practice questions and answers are the most ideal way to get equipped and pass IT tests. I scored 88% on my PMI pmi-rmp exam, and my associates have used Killexams.com material to obtain various certifications. It is a reliable learning tool and one of my top choices. |
Features of iPass4sure PMI-RMP Exam
- Files: PDF / Test Engine
- Premium Access
- Online Test Engine
- Instant download Access
- Comprehensive Q&A
- Success Rate
- Real Questions
- Updated Regularly
- Portable Files
- Unlimited Download
- 100% Secured
- Confidentiality: 100%
- Success Guarantee: 100%
- Any Hidden Cost: $0.00
- Auto Recharge: No
- Updates Intimation: by Email
- Technical Support: Free
- PDF Compatibility: Windows, Android, iOS, Linux
- Test Engine Compatibility: Mac / Windows / Android / iOS / Linux
Premium PDF with 443 Q&A
Get Full VersionAll PMI Exams
PMI ExamsCertification and Entry Test Exams
Complete exam list