Answer: B
QUESTION: 611
During which process would you obtain stakeholders' formal acceptance of the completed
project scope?
A. Quality control
B. Scope verification
C. Scope control
D. Close project
Answer: B
QUESTION: 612
The initial development of a Project Scope Management plan uses which technique?
A. Alternatives identification
B. Scope decomposition
C. Expert judgment
D. Product analysis
Answer: C
QUESTION: 613
What is a hierarchically organized depiction of the identified project risks arranged by
risk category?
A. Risk register
B. Risk breakdown structure (RBS)
C. Risk management plan
D. Risk category
Answer: B
QUESTION: 614
Which is a tool or technique used in scope definition?
200
A. Templates, forms and standards
B. Change requests
C. Stakeholder analysis
D. Project assumptions
Answer: C
QUESTION: 615
What is
the total float of the critical path?
A. Can be any number
B. Zero or positive
C. Zero or negative
D. Depends on the calendar
Answer: C
QUESTION: 616
Which of the following is the correct network diagram for the table?
A. Begin - A - C - D - E - End - B - D
B. Begin - A - B - C - D - E - End
C. Begin - A - B - D - E - End A - C - D
D. Begin - A - C - D - E - End - B - C
Answer: A
QUESTION: 617
201
Which of the following is a schedule network analysis technique that takes limited
resources into account?
A. Network reserve analysis
B. Critical chain method
C. Lead and lag adjustment
D. Critical path method
Answer: B
QUESTION: 618
Fast tracking is a schedule compression technique used to shorten the project schedule
without changing project scope. Which of the following can result from fast tracking?
A. The risk of achieving the shortened project time is increased.
B. The critical path will have positive total float.
C. Contingency reserves are released for redeployment by the project manager.
D. Duration buffers are added to maintain a focus on planned activity durations.
Answer: A
QUESTION: 619
Which estimating technique uses the actual costs of previous similar projects as a
basis
for estimating the costs of the current project?
A. Analogous
B. Parametric
C. Bottom-up
D. Top-down
Answer: A
QUESTION: 620
Your project has an EV of 100 work-days, an AC of 120 work-days, and a PV of 80
work-days. What should be your concern?
A. There is a cost under run.
202
B. There is a cost overrun.
C. May not meet deadline.
D. The project is 20 days behind schedule.
Answer: B
QUESTION: 621
project team
Which illustrates the connection between work that needs to be done and its
members?
A. Work breakdown structure
B. Network diagrams
C. Staffing management plan
D. Responsibility matrix
Answer: D
QUESTION: 622
When can pre-assignment of project team members occur?
A. When the project uses capital expenditures.
B. When the required staff can be acquired from outside sources.
C. When the project would be ignored due to travel expenses.
D. When the project is the result of specific people being promised as part of a
competitive proposal.
Answer: D
QUESTION: 623
Which process uses occurrence probability and impact on project objectives to assess the
priority of identified risks?
A. Risk identification
B. Qualitative risk analysis
C. Risk management planning
D. Quantitative risk analysis
203
Answer: B
QUESTION: 624
In which process might you use risk reassessment as a tool and technique?
A. Qualitative risk analysis
B. Risk monitoring and control
C. Monitor and control project work
D. Risk response planning
Answer: B
QUESTION: 625
A contract management plan is a subsidiary of what other type of plan?
A. Resource plan
B. Project management plan
C. Cost control plan
D. Expected monetary value plan
Answer: B
204
User: Panya*****![]() ![]() ![]() ![]() ![]() Studying for the FOUNDATION CERTIFICATE IN PROJECT MANAGEMENT exam was a challenging experience, with so many complex subjects to cover. However, using killexams.com study material boosted my self-confidence to pass the exam with an exceptional score of 93%. Although some of the questions were tricky, the accurate answers provided by killexams.com helped me mark the right answers. |
User: Tonja*****![]() ![]() ![]() ![]() ![]() The killexams.com iseb-pm1 material provided notable help for me while preparing for the exam. The material was clear and easy to understand, which helped me achieve an excellent result. |
User: Ibrahim*****![]() ![]() ![]() ![]() ![]() The quality of killexams.com is excellent, providing candidates with sufficient support in their ISEB-PM1 exam training. All the materials that I used for ISEB-PM1 exam training were of high quality, and they helped me to prepare for the exam quickly. |
User: Olenka*****![]() ![]() ![]() ![]() ![]() I found the precise answers to be easy to remember. I was able to make all the right responses during the ISEB-PM1 exam because of my familiarity with the Killexams.com Questions and Answers. I preferred using Killexams.com for my exam preparation, which I completed within just 12 days. The presentation of the study material was simple and without any unnecessarily lengthy answers or confusing explanations. Even topics that are generally difficult were taught superbly. |
User: Mitre*****![]() ![]() ![]() ![]() ![]() Thanks to killexams.com, I no longer feel like I am taking mid-terms. Their practice tests have been a great companion to me while studying for the ISEB-PM1 exam. The educators have been supportive and helpful in answering all my questions, regardless of the time of day. |
Features of iPass4sure ISEB-PM1 Exam
- Files: PDF / Test Engine
- Premium Access
- Online Test Engine
- Instant download Access
- Comprehensive Q&A
- Success Rate
- Real Questions
- Updated Regularly
- Portable Files
- Unlimited Download
- 100% Secured
- Confidentiality: 100%
- Success Guarantee: 100%
- Any Hidden Cost: $0.00
- Auto Recharge: No
- Updates Intimation: by Email
- Technical Support: Free
- PDF Compatibility: Windows, Android, iOS, Linux
- Test Engine Compatibility: Mac / Windows / Android / iOS / Linux
Premium PDF with 625 Q&A
Get Full VersionAll ISEB Exams
ISEB ExamsCertification and Entry Test Exams
Complete exam list