PMI CCE-CCC Questions & Answers

Full Version: 95 Q&A


Latest CCE-CCC Exam Questions and Practice Tests 2024 - Killexams.com

Latest CCE-CCC Practice Tests with Actual Questions


Get Complete pool of questions with Premium PDF and Test Engine


Exam Code : CCE-CCC
Exam Name : Certified Cost Consultant / Cost Engineer (AACE International)
Vendor Name :
"PMI"








CCE-CCC Dumps CCE-CCC Braindumps

CCE-CCC Real Questions CCE-CCC Practice Test CCE-CCC Actual Questions


killexams.com


PMI


CCE-CCC


Certified Cost Consultant / Cost Engineer (AACE International)


https://killexams.com/pass4sure/exam-detail/CCE-CCC


:


QUESTION 87


The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If steel costs $1800/ton at the end of Year 3, what is the price of steel at the end of Year 4? A. $1890/ton

  1. $1863/ton

  2. $1948/ton D. $1836/ton




Answer: D


:


QUESTION 88

AACE International defines as a technique of economic evaluation that sums over a given study period, the costs of initial investment, replacements, operations, and maintenance/repair; expressed in either present or annual value terms.


  1. Risk analysis

  2. Benefit/Cost ratio (B/C) method

  3. Net present worth method

  4. Life cycle costs method (LCC)




Answer: D


:


QUESTION 89

can be defined as the determination of that course of action or combination of alternatives that yields either the lowest cost or the highest profit.


  1. Economic optimization

  2. Simulation

  3. Linear programming

  4. Dynamic programming




Answer: D


:


QUESTION 90

What is executed in connection with a contract and secures the performance and fulfillment of all the undertakings, covenants, terms, conditions and agreements contained in the contract?


  1. Liability insurance

  2. Performance bond

  3. Bid bond

  4. Surety bond




Answer: B


:


QUESTION 91

Productivity increases with time. This improvement is commonly associated with improvements in efficiency brought about by increased experience and skill levels. What does this scenario describe?


  1. Productivity efficiency factor

  2. Value engineering

  3. Cash flow

  4. The learning curve




Answer: D


:


QUESTION 92

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. Which of the following methods a used for creating critical path schedules:


  1. Precedence diagram method

  2. Precedence and arrow diagram methods only

  3. Gantt chart (bar chart) method

  4. Arrow diagram method




Answer: B


A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.


You are reporting on a roadway project, which was estimated to be 10 miles of road. It was scheduled to be completed in 16 weeks, which is this week. According to your calculations, the project has a schedule performance index of 0.80. What would you advise the management about the scheduled completion date?


  1. Project will be completed in 20 more weeks

  2. Project will be completed this week - on schedule

  3. Project will be completed in 4 more weeks

  4. Project will be completed in 12.8 more weeks




Answer: C


:


QUESTION 94

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.


The project scheduler left the company and has left unfinished work. You have been hired as the new project scheduler and must update the existing schedule. What will be your first task?


  1. Recalculate the early finish for each activity

  2. Recalculate the early start for each activity

  3. Update the remaining duration for each activity

  4. Recalculate the critical path




Answer: D


A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.


The recognition of loss of value of a natural resource used in the production process is referred to as:


  1. Capital reduction

  2. Net loss

  3. Depreciation

  4. Depletion




Answer: D


:


User: Oleg*****

Thanks to the accurate questions, topics, and practice courses provided by killexams.com, I managed to pass the CCE-CCC exam with ease. The format of the course is highly convenient, allowing you to test in different formats and exercise sessions that suit you the best. The exam simulator is a fantastic tool that completely simulates the actual exam, which is crucial for the CCE-CCC exam with its unique question types. I will definitely use killexams.com for my upcoming certification tests.
User: Tawnya*****

I never thought I could pass the cce-ccc exam so easily, but thanks to killexams.com, I did. The custom-designed material helped me understand the concepts and answer even the unknown questions. It met all my requirements throughout the training. I answered 90% of the questions within the guide, which helped me save time for the unknown ones.
User: Abdallah*****

I wanted to express my gratitude to killexams.com for helping me pass my certified cost consultant / cost engineer (aace international) exam with a score of 90%. I subscribed to their test materials and found them to be incredibly helpful. Thanks again for your excellent assistance!
User: Lydie*****

The Killexams.com questions and answers provided me with an insight into what was expected in the cce-ccc exam. With only 10 days of guidance, I managed to organize myself and complete all the questions in 80 minutes. It made me understand how to manage time and memorize all the subjects quickly.
User: Valeria*****

I often skip lessons, which is a big problem for me if my parents find out. I needed to cover up my mistakes and ensure that they would believe in me again. I knew that the only way to do that was to perform well in my CCE-CCC exam, which was very close. Thanks to killexams.com, I received the right instructions, and I was able to pass the exam. Thanks!

Features of iPass4sure CCE-CCC Exam

  • Files: PDF / Test Engine
  • Premium Access
  • Online Test Engine
  • Instant download Access
  • Comprehensive Q&A
  • Success Rate
  • Real Questions
  • Updated Regularly
  • Portable Files
  • Unlimited Download
  • 100% Secured
  • Confidentiality: 100%
  • Success Guarantee: 100%
  • Any Hidden Cost: $0.00
  • Auto Recharge: No
  • Updates Intimation: by Email
  • Technical Support: Free
  • PDF Compatibility: Windows, Android, iOS, Linux
  • Test Engine Compatibility: Mac / Windows / Android / iOS / Linux

Premium PDF with 95 Q&A

Get Full Version

All PMI Exams

PMI Exams

Certification and Entry Test Exams

Complete exam list