Certification Practice Test | PDF Questions | Actual Questions | Test Engine | Pass4Sure
CCE-CCC : Certified Cost Consultant / Cost Engineer (AACE International) Exam

PMI CCE-CCC Questions & Answers
Full Version: 95 Q&A
CCE-CCC Dumps CCE-CCC Braindumps
CCE-CCC Real Questions CCE-CCC Practice Test CCE-CCC Actual Questions
killexams.com
PMI
CCE-CCC
Certified Cost Consultant / Cost Engineer (AACE International)
https://killexams.com/pass4sure/exam-detail/CCE-CCC
:
QUESTION 87
The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
If steel costs $1800/ton at the end of Year 3, what is the price of steel at the end of Year 4? A. $1890/ton
$1863/ton
$1948/ton D. $1836/ton
Answer: D
:
QUESTION 88
AACE International defines as a technique of economic evaluation that sums over a given study period, the costs of initial investment, replacements, operations, and maintenance/repair; expressed in either present or annual value terms.
Risk analysis
Benefit/Cost ratio (B/C) method
Net present worth method
Life cycle costs method (LCC)
Answer: D
:
QUESTION 89
can be defined as the determination of that course of action or combination of alternatives that yields either the lowest cost or the highest profit.
Economic optimization
Simulation
Linear programming
Dynamic programming
Answer: D
:
QUESTION 90
What is executed in connection with a contract and secures the performance and fulfillment of all the undertakings, covenants, terms, conditions and agreements contained in the contract?
Liability insurance
Performance bond
Bid bond
Surety bond
Answer: B
:
QUESTION 91
Productivity increases with time. This improvement is commonly associated with improvements in efficiency brought about by increased experience and skill levels. What does this scenario describe?
Productivity efficiency factor
Value engineering
Cash flow
The learning curve
Answer: D
:
QUESTION 92
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. Which of the following methods a used for creating critical path schedules:
Precedence diagram method
Precedence and arrow diagram methods only
Gantt chart (bar chart) method
Arrow diagram method
Answer: B
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
You are reporting on a roadway project, which was estimated to be 10 miles of road. It was scheduled to be completed in 16 weeks, which is this week. According to your calculations, the project has a schedule performance index of 0.80. What would you advise the management about the scheduled completion date?
Project will be completed in 20 more weeks
Project will be completed this week - on schedule
Project will be completed in 4 more weeks
Project will be completed in 12.8 more weeks
Answer: C
:
QUESTION 94
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The project scheduler left the company and has left unfinished work. You have been hired as the new project scheduler and must update the existing schedule. What will be your first task?
Recalculate the early finish for each activity
Recalculate the early start for each activity
Update the remaining duration for each activity
Recalculate the critical path
Answer: D
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The recognition of loss of value of a natural resource used in the production process is referred to as:
Capital reduction
Net loss
Depreciation
Depletion
Answer: D
:
User: Levka*****![]() ![]() ![]() ![]() ![]() Thanks to killexams.com, I no longer feel alone during exams. I have found an excellent study partner in the form of their study materials. Moreover, their instructors are always available to guide me, regardless of the time of day. During my exams, I received the same consistent level of guidance, and all my questions were promptly answered. I am truly grateful to the instructors at killexams.com for their excellent and friendly support that helped me pass my tough cce-ccc certification exam. The cce-ccc study practice tests and cce-ccc exam simulator were truly amazing resources. |
User: Nastasya*****![]() ![]() ![]() ![]() ![]() Killexams.com is trustworthy, and everything provided is reliable. I had heard excellent reviews about Killexams, so I purchased it to prepare for my cce-ccc exam. It was as good as promised, with high-quality materials and an easy practice exam. I passed the cce-ccc exam with a score of 96%. |
User: Rodina*****![]() ![]() ![]() ![]() ![]() Notes and questions made my cce-ccc exam preparation smooth, leading to a 92% score. Their well-crafted materials and exam simulator, especially for topics like trainer communication, were outstanding. I am grateful for their excellent work. |
User: Isla*****![]() ![]() ![]() ![]() ![]() At the dinner table the other night, my father asked me if I was going to fail my upcoming cce-ccc exam. I responded confidently with a resounding "No way." Thanks to Killexams.com, I was able to keep my word and pass the exam with excellent results. I am thankful for their help and support. |
User: Santino*****![]() ![]() ![]() ![]() ![]() Customized cce-ccc materials made even unfamiliar questions manageable. Their resources were inspiring and energizing, leading me to pass with confidence. |
Features of iPass4sure CCE-CCC Exam
- Files: PDF / Test Engine
- Premium Access
- Online Test Engine
- Instant download Access
- Comprehensive Q&A
- Success Rate
- Real Questions
- Updated Regularly
- Portable Files
- Unlimited Download
- 100% Secured
- Confidentiality: 100%
- Success Guarantee: 100%
- Any Hidden Cost: $0.00
- Auto Recharge: No
- Updates Intimation: by Email
- Technical Support: Free
- PDF Compatibility: Windows, Android, iOS, Linux
- Test Engine Compatibility: Mac / Windows / Android / iOS / Linux
Premium PDF with 95 Q&A
Get Full VersionAll PMI Exams
PMI ExamsCertification and Entry Test Exams
Complete exam list