PMI CCE-CCC Questions & Answers

Full Version: 95 Q&A


Latest CCE-CCC Exam Questions and Practice Tests 2024 - Killexams.com

Latest CCE-CCC Practice Tests with Actual Questions


Get Complete pool of questions with Premium PDF and Test Engine


Exam Code : CCE-CCC
Exam Name : Certified Cost Consultant / Cost Engineer (AACE International)
Vendor Name :
"PMI"








CCE-CCC Dumps CCE-CCC Braindumps

CCE-CCC Real Questions CCE-CCC Practice Test CCE-CCC Actual Questions


killexams.com


PMI


CCE-CCC


Certified Cost Consultant / Cost Engineer (AACE International)


https://killexams.com/pass4sure/exam-detail/CCE-CCC


:


QUESTION 87


The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If steel costs $1800/ton at the end of Year 3, what is the price of steel at the end of Year 4? A. $1890/ton

  1. $1863/ton

  2. $1948/ton D. $1836/ton




Answer: D


:


QUESTION 88

AACE International defines as a technique of economic evaluation that sums over a given study period, the costs of initial investment, replacements, operations, and maintenance/repair; expressed in either present or annual value terms.


  1. Risk analysis

  2. Benefit/Cost ratio (B/C) method

  3. Net present worth method

  4. Life cycle costs method (LCC)




Answer: D


:


QUESTION 89

can be defined as the determination of that course of action or combination of alternatives that yields either the lowest cost or the highest profit.


  1. Economic optimization

  2. Simulation

  3. Linear programming

  4. Dynamic programming




Answer: D


:


QUESTION 90

What is executed in connection with a contract and secures the performance and fulfillment of all the undertakings, covenants, terms, conditions and agreements contained in the contract?


  1. Liability insurance

  2. Performance bond

  3. Bid bond

  4. Surety bond




Answer: B


:


QUESTION 91

Productivity increases with time. This improvement is commonly associated with improvements in efficiency brought about by increased experience and skill levels. What does this scenario describe?


  1. Productivity efficiency factor

  2. Value engineering

  3. Cash flow

  4. The learning curve




Answer: D


:


QUESTION 92

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. Which of the following methods a used for creating critical path schedules:


  1. Precedence diagram method

  2. Precedence and arrow diagram methods only

  3. Gantt chart (bar chart) method

  4. Arrow diagram method




Answer: B


A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.


You are reporting on a roadway project, which was estimated to be 10 miles of road. It was scheduled to be completed in 16 weeks, which is this week. According to your calculations, the project has a schedule performance index of 0.80. What would you advise the management about the scheduled completion date?


  1. Project will be completed in 20 more weeks

  2. Project will be completed this week - on schedule

  3. Project will be completed in 4 more weeks

  4. Project will be completed in 12.8 more weeks




Answer: C


:


QUESTION 94

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.


The project scheduler left the company and has left unfinished work. You have been hired as the new project scheduler and must update the existing schedule. What will be your first task?


  1. Recalculate the early finish for each activity

  2. Recalculate the early start for each activity

  3. Update the remaining duration for each activity

  4. Recalculate the critical path




Answer: D


A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.


The recognition of loss of value of a natural resource used in the production process is referred to as:


  1. Capital reduction

  2. Net loss

  3. Depreciation

  4. Depletion




Answer: D


:


User: Nadine*****

Passing the CCE-CCC exam proved quite challenging for me until I discovered killexams questions and answers. Certain topics appeared exceedingly difficult, and despite my efforts to study from books, time constraints hindered my progress. In the end, the practice tests provided by Killexams aided me in understanding these complex topics and completing my preparation within a mere ten days. I am grateful for this invaluable guide and extend my heartfelt thanks to Killexams.
User: Lenin*****

The killexams.com cce-ccc material proved to be a great help for me in preparing for and passing my exam. It provided me with the necessary guidance and understanding to face any topic or situation that came my way. I was worried initially, but going back to the cce-ccc Questions and Answers made me feel confident that I understood the material. After using the killexams.com material, the cce-ccc exam seemed very easy, and I got an awesome result. I am now ready to pursue the next level of PMI certifications.
User: Mohammed*****

Thanks to killexams.com, I was able to pass the cce-ccc exam with a score of 89%. Their exam arrangement was spot on and helped me tremendously.
User: Slava*****

Both the killexams.com Questions and Answers practice test and CCE-CCC exam Simulator were essential to my success in the exam. The material helped me analyze my weaknesses and focus my efforts on the areas where I needed improvement. I was able to prepare adequately and pass the exam with ease. I wish everyone the best of luck in their exams.
User: Laika*****

Last month, I took the CCE-CCC exam and passed it thanks to my preparation with the Killexams.com kit. It is a great exam practice test, more reliable than I expected. All questions are valid, and it includes a lot of preparation material. I passed with over 97%, the best score on the CCE-CCC exam. I am not sure why so few IT professionals know about Killexams, or maybe it is just my conservative environment. In any case, I will recommend it to my friends, and it will be helpful to many.

Features of iPass4sure CCE-CCC Exam

  • Files: PDF / Test Engine
  • Premium Access
  • Online Test Engine
  • Instant download Access
  • Comprehensive Q&A
  • Success Rate
  • Real Questions
  • Updated Regularly
  • Portable Files
  • Unlimited Download
  • 100% Secured
  • Confidentiality: 100%
  • Success Guarantee: 100%
  • Any Hidden Cost: $0.00
  • Auto Recharge: No
  • Updates Intimation: by Email
  • Technical Support: Free
  • PDF Compatibility: Windows, Android, iOS, Linux
  • Test Engine Compatibility: Mac / Windows / Android / iOS / Linux

Premium PDF with 95 Q&A

Get Full Version

All PMI Exams

PMI Exams

Certification and Entry Test Exams

Complete exam list