Certification Practice Test | PDF Questions | Actual Questions | Test Engine | Pass4Sure
CCE-CCC : Certified Cost Consultant / Cost Engineer (AACE International) Exam

PMI CCE-CCC Questions & Answers
Full Version: 95 Q&A
CCE-CCC Dumps CCE-CCC Braindumps
CCE-CCC Real Questions CCE-CCC Practice Test CCE-CCC Actual Questions
killexams.com
PMI
CCE-CCC
Certified Cost Consultant / Cost Engineer (AACE International)
https://killexams.com/pass4sure/exam-detail/CCE-CCC
:
QUESTION 87
The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
If steel costs $1800/ton at the end of Year 3, what is the price of steel at the end of Year 4? A. $1890/ton
1. $1863/ton
2. $1948/ton D. $1836/ton
Answer: D
:
QUESTION 88
AACE International defines as a technique of economic evaluation that sums over a given study period, the costs of initial investment, replacements, operations, and maintenance/repair; expressed in either present or annual value terms.
1. Risk analysis
2. Benefit/Cost ratio (B/C) method
3. Net present worth method
4. Life cycle costs method (LCC)
Answer: D
:
QUESTION 89
can be defined as the determination of that course of action or combination of alternatives that yields either the lowest cost or the highest profit.
1. Economic optimization
2. Simulation
3. Linear programming
4. Dynamic programming
Answer: D
:
QUESTION 90
What is executed in connection with a contract and secures the performance and fulfillment of all the undertakings, covenants, terms, conditions and agreements contained in the contract?
1. Liability insurance
2. Performance bond
3. Bid bond
4. Surety bond
Answer: B
:
QUESTION 91
Productivity increases with time. This improvement is commonly associated with improvements in efficiency brought about by increased experience and skill levels. What does this scenario describe?
1. Productivity efficiency factor
2. Value engineering
3. Cash flow
4. The learning curve
Answer: D
:
QUESTION 92
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. Which of the following methods a used for creating critical path schedules:
1. Precedence diagram method
2. Precedence and arrow diagram methods only
3. Gantt chart (bar chart) method
4. Arrow diagram method
Answer: B
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
You are reporting on a roadway project, which was estimated to be 10 miles of road. It was scheduled to be completed in 16 weeks, which is this week. According to your calculations, the project has a schedule performance index of 0.80. What would you advise the management about the scheduled completion date?
1. Project will be completed in 20 more weeks
2. Project will be completed this week - on schedule
3. Project will be completed in 4 more weeks
4. Project will be completed in 12.8 more weeks
Answer: C
:
QUESTION 94
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The project scheduler left the company and has left unfinished work. You have been hired as the new project scheduler and must update the existing schedule. What will be your first task?
1. Recalculate the early finish for each activity
2. Recalculate the early start for each activity
3. Update the remaining duration for each activity
4. Recalculate the critical path
Answer: D
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The recognition of loss of value of a natural resource used in the production process is referred to as:
1. Capital reduction
2. Net loss
3. Depreciation
4. Depletion
Answer: D
:
User: Tamryn*****![]() ![]() ![]() ![]() ![]() cce-ccc prep materials helped me score 92%. Their unique problem-solving approach simplified even the toughest questions. |
User: Rubal*****![]() ![]() ![]() ![]() ![]() Passing the CCE-CCC exam with Killexams.com was a significant achievement, bringing me a sense of pride and recognition. Their high-quality materials provided the support I needed to succeed and make my mark. |
User: Lee*****![]() ![]() ![]() ![]() ![]() I highly recommend Killexams.com for the cce-ccc exam. Their exam simulator is unmatched, and I scored 97% after just ten days of study. The closest thing to the real exam—worth every penny. |
User: Todor*****![]() ![]() ![]() ![]() ![]() Practice tests were crucial in helping me pass the cce-ccc exam on my first attempt. The exam simulator and question-answer format aligned perfectly with my professional experience, giving me a clear understanding of the exam content. I am grateful for their high-quality study materials and recommend them to all candidates. |
User: Leonardo*****![]() ![]() ![]() ![]() ![]() The practice tests provided by Killexams.com were fantastic. Even though 76% is enough to pass the exam, I scored 92% marks on the real cce-ccc exam. All credit goes to Killexams.com. It is tough to imagine that I could have passed the exam with any other product. This is an excellent product, and I highly recommend it. |
Features of iPass4sure CCE-CCC Exam
- Files: PDF / Test Engine
- Premium Access
- Online Test Engine
- Instant download Access
- Comprehensive Q&A
- Success Rate
- Real Questions
- Updated Regularly
- Portable Files
- Unlimited Download
- 100% Secured
- Confidentiality: 100%
- Success Guarantee: 100%
- Any Hidden Cost: $0.00
- Auto Recharge: No
- Updates Intimation: by Email
- Technical Support: Free
- PDF Compatibility: Windows, Android, iOS, Linux
- Test Engine Compatibility: Mac / Windows / Android / iOS / Linux
Premium PDF with 95 Q&A
Get Full VersionAll PMI Exams
PMI ExamsCertification and Entry Test Exams
Complete exam list