QUESTION 87
The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu,
to reference during your response/choice of responses.
If steel costs $1800/ton at the end of Year 3, what is the price of steel at the end of Year 4?
A. $1890/ton
B. $1863/ton
C. $1948/ton
D. $1836/ton
Answer: D
:
QUESTION 88
AACE International defines _____________as a technique of economic evaluation that sums over a given study period, the costs of initial investment,
replacements, operations, and maintenance/repair; expressed in either present or annual value terms.
A. Risk analysis
B. Benefit/Cost ratio (B/C) method
C. Net present worth method
D. Life cycle costs method (LCC)
Answer: D
:
QUESTION 89
______________can be defined as the determination of that course of action or combination of alternatives that yields either the lowest cost or the
highest profit.
A. Economic optimization
B. Simulation
C. Linear programming
D. Dynamic programming
Answer: D
:
QUESTION 90
What is executed in connection with a contract and secures the performance and fulfillment of all the undertakings, covenants, terms, conditions and
agreements contained in the contract?
A. Liability insurance
B. Performance bond
C. Bid bond
D. Surety bond
Answer: B
:
QUESTION 91
Productivity increases with time. This improvement is commonly associated with improvements in efficiency brought about by increased experience and
skill levels. What does this scenario describe?
A. Productivity efficiency factor
B. Value engineering
C. Cash flow
D. The learning curve
Answer: D
:
QUESTION 92
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded.
Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the
design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
Which of the following methods a used for creating critical path schedules:
A. Precedence diagram method
B. Precedence and arrow diagram methods only
C. Gantt chart (bar chart) method
D. Arrow diagram method
Answer: B
:
QUESTION 93
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded.
Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the
design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
You are reporting on a roadway project, which was estimated to be 10 miles of road. It was scheduled to be completed in 16 weeks, which is this week.
According to your calculations, the project has a schedule performance index of 0.80. What would you advise the management about the scheduled
completion date?
A. Project will be completed in 20 more weeks
B. Project will be completed this week - on schedule
C. Project will be completed in 4 more weeks
D. Project will be completed in 12.8 more weeks
Answer: C
:
QUESTION 94
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded.
Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the
design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The project scheduler left the company and has left unfinished work. You have been hired as the new project scheduler and must update the existing
schedule. What will be your first task?
A. Recalculate the early finish for each activity
B. Recalculate the early start for each activity
C. Update the remaining duration for each activity
D. Recalculate the critical path
Answer: D
:
QUESTION 95
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded.
Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the
design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The recognition of loss of value of a natural resource used in the production process is referred to as:
A. Capital reduction
B. Net loss
C. Depreciation
D. Depletion
Answer: D
:
User: Grace*****![]() ![]() ![]() ![]() ![]() I passed this exam last fall, and over 90% of the questions were valid at the time. killexams.com cares to update their materials frequently, so they are highly likely to still be valid. They are a great organization that has helped me more than once. |
User: Zoe*****![]() ![]() ![]() ![]() ![]() Thanks to Killexams.com, I was able to request and practice for a week before taking the CCE-CCC exam, which I passed with an impressive 89% marks. This is what a great exam arrangement should look like for everyone. The website superb collection of exam association practice tests and materials made it possible for me to become a CCE-CCC certified companion. The questions are valid, and the exam simulator works efficiently without any problems. I highly recommend Killexams.com Questions and Answers. |
User: Taisiya*****![]() ![]() ![]() ![]() ![]() Thanks to the questions and answers from killexams.com, I was efficient enough to pass this exam easily. I answered 90 out of 95 questions within the given timeframe and passed with ease. I never thought that passing the CCE-CCC exam was possible, given my full-time work and exam preparation. But I came across killexams.com and decided to give it a try. |
User: Florence*****![]() ![]() ![]() ![]() ![]() Preparing for the cce-ccc practice exam requires a lot of hard work and time, including the complex problem of time management. However, Killexams.com has resolved this problem by providing useful time schedules and instructional guides for the cce-ccc practice exam. By using their certification, one can easily complete their syllabus for the cce-ccc practice exam and score high marks. |
User: Ludis*****![]() ![]() ![]() ![]() ![]() I highly recommend killexams.com to anyone considering purchasing exam preparation materials. It is a fully valid and reliable preparation tool and a great option for those who cannot afford full-time courses. (I believe those are a waste of time and money, especially when Killexams is available.) And in case you were wondering, the questions are real! |
Features of iPass4sure CCE-CCC Exam
- Files: PDF / Test Engine
- Premium Access
- Online Test Engine
- Instant download Access
- Comprehensive Q&A
- Success Rate
- Real Questions
- Updated Regularly
- Portable Files
- Unlimited Download
- 100% Secured
- Confidentiality: 100%
- Success Guarantee: 100%
- Any Hidden Cost: $0.00
- Auto Recharge: No
- Updates Intimation: by Email
- Technical Support: Free
- PDF Compatibility: Windows, Android, iOS, Linux
- Test Engine Compatibility: Mac / Windows / Android / iOS / Linux
Premium PDF with 95 Q&A
Get Full VersionAll PMI Exams
PMI ExamsCertification and Entry Test Exams
Complete exam list