QUESTION: 109
It is recommended that when beginning a 5S program it be started in a pilot work area for learning and demonstration purposes then it is expended throughout the plant.
True
False
Answer: A
QUESTION: 110
As part of a Visual Factory plan are created and utilized to identify areas in need of cleaning and organization.
Flashing lights
Soft horns
Kanban cards
Operator announcement programs
Answer: C
QUESTION: 111
One of the 5S approaches to eliminating waste is to organize all tools, information and inventory utilized at a workstation in such a manner that the operator knows exactly where things are when needed. This 5S tool is called .
Standardizing
Scheduling
Sustaining
Straightening
Answer: D
QUESTION: 112
The Control Plan is the road map to sustaining the improvements made through the Lean Six Sigma project and should therefore involve keeping the up to date as a means of supporting the Response Plan in case a defect is noticed.
X-Y Diagram
Shewhart Chart
FMEA
Customer Service Plan
Answer: C
QUESTION: 113
To minimize waste through the application of Lean Principles we do which of the following?
Collect sample data
Keep the work area clean and organized
Calibrate our measurement tools
Survey the customer
Answer: B
QUESTION: 114
A Lean Principle that states the process of eliminating waste is a continual process requiring one to always be on the lookout for ways to reduce the seven elements of waste is known as
Ishikawa
Kaizen
Kanban
Muda
Answer: B
QUESTION: 115
An important factor in a viable is to determine who, when and to what level various personnel must be trained to maintain the improvements made to a process.
Control Plan
FMEA
Standard Operating Procedure
Process Map
Answer: C
QUESTION: 116
A Monitoring Plan put into place at the conclusion of a project will provide for adequate systems with key metric readouts indicating out-of-spec conditions.
True
False
Answer: A
QUESTION: 117
The Control Plan is created following the finalization of the Measure Phase and can be closed when?
After the project costs have been recouped
When the Champion says so
Never, a Control Plan must stay in place
At the fiscal yearend of the business
Answer: C
QUESTION: 118
Systems and structures are the basis for allowing people to change their behaviors permanently and are accomplished through which of the following?
Documented performance objectives
Defined procedures
Accurate job descriptions
Incentive compensation
All of these answers are correct
Answer: E
QUESTION: 119
To reduce the people or operator introduced defects into a process it is best if a Belt can design and implement a means of into the process.
Measurement automation
Operator alertness
Full Automation
Constant supervision
Answer: C
QUESTION: 120
Upon completion of a project a Belt must complete the Documentation Plan then transfer responsibility for this to the .
Project Review Committee
Division Manager
Sales Team
Process Owner
Answer: D
User: Leanne*****![]() ![]() ![]() ![]() ![]() Killexams.com is designed to help all students achieve success, and I am certainly no exception. Purchasing the CLSSYB exam guide proved to be the right decision, and using the CLSSYB exam engine helped me score an impressive 92%. I am truly grateful for the team at Killexams.com for providing me with the resources I needed to succeed. |
User: Théo*****![]() ![]() ![]() ![]() ![]() While 76% is decent, Killexams.com’s practice tests helped me achieve 92% on the clssyb exam. Their materials were outstanding, and I cannot imagine using any other product. I will recommend them to everyone. |
User: Kathleen*****![]() ![]() ![]() ![]() ![]() Passing the CLSSYB certification required more than just memorizing killexams.com’s Questions and Answers, but their testprep materials made the process easier. While some exam questions were unexpected, their comprehensive resources enabled me to tackle them confidently, resulting in a strong pass. I am thankful to Jack from England for recommending killexams.com. |
User: Mila*****![]() ![]() ![]() ![]() ![]() Preparing for the CLSSYB exam felt daunting due to its complexity, but killexams.com turned that challenge into an opportunity. Their daily-updated practice questions closely resembled the real exam, giving me the edge I needed. By reviewing their testprep materials, I was able to score an impressive 91% while answering 58 questions in just 90 minutes. Killexams.com made the preparation process efficient and effective, and I highly recommend their resources to anyone tackling this certification. |
User: Betty*****![]() ![]() ![]() ![]() ![]() With only 12 days left before the clssyb exam, I was overwhelmed. Killexams.com’s concise answers were a lifesaver—I memorized them quickly and scored 91%. Their rapid-reference materials were exactly what I needed to stay on track. |
Features of iPass4sure CLSSYB Exam
- Files: PDF / Test Engine
- Premium Access
- Online Test Engine
- Instant download Access
- Comprehensive Q&A
- Success Rate
- Real Questions
- Updated Regularly
- Portable Files
- Unlimited Download
- 100% Secured
- Confidentiality: 100%
- Success Guarantee: 100%
- Any Hidden Cost: $0.00
- Auto Recharge: No
- Updates Intimation: by Email
- Technical Support: Free
- PDF Compatibility: Windows, Android, iOS, Linux
- Test Engine Compatibility: Mac / Windows / Android / iOS / Linux
Premium PDF with 120 Q&A
Get Full VersionAll GAQM Exams
GAQM ExamsCertification and Entry Test Exams
Complete exam list