QUESTION: 109
It is recommended that when beginning a 5S program it be started in a pilot work
area for learning and demonstration purposes then it is expended throughout the
plant.
A. True
B. False
Answer: A
QUESTION: 110
As part of a Visual Factory plan are created and utilized to identify areas in
need of cleaning and organization.
A. Flashing lights
B. Soft horns
C. Kanban cards
D. Operator announcement programs
Answer: C
QUESTION: 111
One of the 5S approaches to eliminating waste is to organize all tools, information
and inventory utilized at a workstation in such a manner that the operator knows
exactly where things are when needed. This 5S tool is called .
A. Standardizing
B. Scheduling
C. Sustaining
D. Straightening
Answer: D
QUESTION: 112
The Control Plan is the road map to sustaining the improvements made through the
Lean Six Sigma project and should therefore involve keeping the up to date as a
means of supporting the Response Plan in case a defect is noticed.
A. X-Y Diagram
B. Shewhart Chart
C. FMEA
D. Customer Service Plan
Answer: C
QUESTION: 113
To minimize waste through the application of Lean Principles we do which of the
following?
A. Collect sample data
B. Keep the work area clean and organized
C. Calibrate our measurement tools
D. Survey the customer
Answer: B
QUESTION: 114
A Lean Principle that states the process of eliminating waste is a continual process
requiring one to always be on the lookout for ways to reduce the seven elements of
waste is known as_________
A. Ishikawa
B. Kaizen
C. Kanban
D. Muda
Answer: B
QUESTION: 115
An important factor in a viable_________ is to determine who, when and to what
level various personnel must be trained to maintain the improvements made to a
process.
A. Control Plan
B. FMEA
C. Standard Operating Procedure
D. Process Map
Answer: C
QUESTION: 116
A Monitoring Plan put into place at the conclusion of a project will provide for
adequate systems with key metric readouts indicating out-of-spec conditions.
A. True
B. False
Answer: A
QUESTION: 117
The Control Plan is created following the finalization of the Measure Phase and
can be closed when?
A. After the project costs have been recouped
B. When the Champion says so
C. Never, a Control Plan must stay in place
D. At the fiscal yearend of the business
Answer: C
QUESTION: 118
Systems and structures are the basis for allowing people to change their behaviors
permanently and are accomplished through which of the following?
A. Documented performance objectives
B. Defined procedures
C. Accurate job descriptions
D. Incentive compensation
E. All of these answers are correct
Answer: E
QUESTION: 119
To reduce the people or operator introduced defects into a process it is best if a
Belt can design and implement a means of into the process.
A. Measurement automation
B. Operator alertness
C. Full Automation
D. Constant supervision
Answer: C
QUESTION: 120
Upon completion of a project a Belt must complete the Documentation Plan then
transfer responsibility for this to the .
A. Project Review Committee
B. Division Manager
C. Sales Team
D. Process Owner
Answer: D

User: Izz*****

For those of you who are short on time and cannot memorize, do not worry. I was in a similar situation, but I found an easy solution with Killexams. Their questions and answers were very helpful and allowed me to grasp the concepts and memorize the difficult parts. The questions were identical to the guide, and I was able to score well. Thanks to Killexams for their useful material.
User: Stanley*****

Can you smell the sweet fragrance of victory? I know I can, and it is a beautiful scent. You can smell it too if you use killexams.com to prepare for your clssyb exam. The facilities here are perfect, and once you are in, you will not be worried about failing at all. I did not fail and did quite well, and so can you. Try it now!
User: Vitali*****

It is easy to put off studying and wait for the right moment to come. But sometimes, you need to take a stand before Its too late. As someone who primarily manages a CLSSYB customer base, I decided to take the certification exam and become the expert in my office. A friend recommended killexams.com, and I tried their demo, loved it, and purchased the full package. The exam simulator is fantastic, and it helped me become the new CLSSYB manager.
User: Ruslan*****

killexams.com provides splendid exam preparation resources for the clssyb exam. I purchased their material because I could not find any reliable books or PDFs to study from. Their practice exams provided real questions that accurately reflected the exam format, with no irrelevant or unnecessary information. I highly recommend killexams.com to anyone taking the clssyb exam.
User: Simon*****

I also used the Killexams.com GAQM test education practice test to prepare for the clssyb exam. Although it was challenging, the material proved to be very helpful in passing the exam.

Features of iPass4sure CLSSYB Exam

  • Files: PDF / Test Engine
  • Premium Access
  • Online Test Engine
  • Instant download Access
  • Comprehensive Q&A
  • Success Rate
  • Real Questions
  • Updated Regularly
  • Portable Files
  • Unlimited Download
  • 100% Secured
  • Confidentiality: 100%
  • Success Guarantee: 100%
  • Any Hidden Cost: $0.00
  • Auto Recharge: No
  • Updates Intimation: by Email
  • Technical Support: Free
  • PDF Compatibility: Windows, Android, iOS, Linux
  • Test Engine Compatibility: Mac / Windows / Android / iOS / Linux

Premium PDF with 120 Q&A

Get Full Version

All GAQM Exams

GAQM Exams

Certification and Entry Test Exams

Complete exam list