ISEB ISEB-PM1 Questions & Answers

Full Version: 625 Q&A


Latest ISEB-PM1 Exam Questions and Practice Tests 2024 - Killexams.com

Latest ISEB-PM1 Practice Tests with Actual Questions


Get Complete pool of questions with Premium PDF and Test Engine


Exam Code : ISEB-PM1
Exam Name : Foundation Certificate in Project Management
Vendor Name :
"ISEB"








ISEB-PM1 Dumps ISEB-PM1 Braindumps

ISEB-PM1 Real Questions ISEB-PM1 Practice Test ISEB-PM1 Actual Questions


ISEB


ISEB-PM1


Foundation Certificate in Project Management


https://killexams.com/pass4sure/exam-detail/ISEB-PM1




Answer: B



Question: 611

During which process would you obtain stakeholders' formal acceptance of the completed project scope?


  1. Quality control

  2. Scope verification

  3. Scope control

  4. Close project




Answer: B



Question: 612

The initial development of a Project Scope Management plan uses which technique?


  1. Alternatives identification

  2. Scope decomposition

  3. Expert judgment

  4. Product analysis




Answer: C



Question: 613

What is a hierarchically organized depiction of the identified project risks arranged by risk category?


  1. Risk register

  2. Risk breakdown structure (RBS)

  3. Risk management plan

  4. Risk category




Answer: B



Question: 614

Which is a tool or technique used in scope definition?


  1. Templates, forms and standards

  2. Change requests

  3. Stakeholder analysis

  4. Project assumptions




Answer: C



Question: 615

What is the total float of the critical path?


  1. Can be any number

  2. Zero or positive

  3. Zero or negative

  4. Depends on the calendar




Answer: C



Question: 616

Which of the following is the correct network diagram for the table?



  1. Begin - A - C - D - E - End - B - D

  2. Begin - A - B - C - D - E - End

  3. Begin - A - B - D - E - End A - C - D

  4. Begin - A - C - D - E - End - B - C




Answer: A



Question: 617


Which of the following is a schedule network analysis technique that takes limited resources into account?


  1. Network reserve analysis

  2. Critical chain method

  3. Lead and lag adjustment

  4. Critical path method




Answer: B



Question: 618

Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?


  1. The risk of achieving the shortened project time is increased.

  2. The critical path will have positive total float.

  3. Contingency reserves are released for redeployment by the project manager.

  4. Duration buffers are added to maintain a focus on planned activity durations.




Answer: A



Question: 619

Which estimating technique uses the actual costs of previous similar projects as a basis for estimating the costs of the current project?


  1. Analogous

  2. Parametric

  3. Bottom-up

  4. Top-down




Answer: A



Question: 620

Your project has an EV of 100 work-days, an AC of 120 work-days, and a PV of 80 work-days. What should be your concern?


  1. There is a cost under run.


  2. There is a cost overrun.

  3. May not meet deadline.

  4. The project is 20 days behind schedule.




Answer: B



Question: 621

Which illustrates the connection between work that needs to be done and its project team members?


  1. Work breakdown structure

  2. Network diagrams

  3. Staffing management plan

  4. Responsibility matrix




Answer: D



Question: 622

When can pre-assignment of project team members occur?


  1. When the project uses capital expenditures.

  2. When the required staff can be acquired from outside sources.

  3. When the project would be ignored due to travel expenses.

  4. When the project is the result of specific people being promised as part of a competitive proposal.




Answer: D



Question: 623

Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?


  1. Risk identification

  2. Qualitative risk analysis

  3. Risk management planning

  4. Quantitative risk analysis




Answer: B



Question: 624

In which process might you use risk reassessment as a tool and technique?


  1. Qualitative risk analysis

  2. Risk monitoring and control

  3. Monitor and control project work

  4. Risk response planning




Answer: B



Question: 625

A contract management plan is a subsidiary of what other type of plan?


  1. Resource plan

  2. Project management plan

  3. Cost control plan

  4. Expected monetary value plan




Answer: B


User: Misha*****

Thanks to Killexams.com, I passed the ISEB ISEB-PM1 exam with a 99% score. Even though I had studied all the chapters, the questions and answers provided sufficient training, and my doubts were cleared in no time. I plan to use their services again in the future and highly recommend them to anyone taking the ISEB ISEB-PM1 exam.
User: Jayden*****

To become iseb-pm1 certified, I had to pass the iseb-pm1 exam. After failing twice, I was pushed to the limit. Fortunately, my cousin provided me with the killexams.com material, and I was very impressed with the Questions and Answers. I secured an 89%, and I am glad that I scored above the passing mark without any problem. The material is correctly formatted and enriched with vital concepts, making it a fantastic resource for the exam.
User: Salvador*****

I am writing this to thank you for your test bank series, which helped me pass the iseb-pm1 exam with a score of 96%. The online exam experience was extraordinary, and the questions were explained in easy-to-understand language. I made the right decision by purchasing your test series, and I am more than satisfied with my choice.
User: Tanny*****

killexams.com was a lifesaver for me during my exam preparation. As the exam dates were getting closer, I was getting more and more nervous. But thanks to the ISEB-PM1 questions and answers that I downloaded and memorized, I passed with ease, answering 87 questions in just 80 minutes. killexams.com truly became my partner, and I will be forever grateful to them for their help.
User: Savina*****

I am delighted to announce that I passed the iseb-pm1 exam with flying colors, scoring 97%, thanks to Killexams.com. I commend the excellent work of the Killexams.com team for providing such a remarkable study practice test. Keep up the great work! I will be using your product for my next exam. Regards from Emma in the Big Apple.

Features of iPass4sure ISEB-PM1 Exam

  • Files: PDF / Test Engine
  • Premium Access
  • Online Test Engine
  • Instant download Access
  • Comprehensive Q&A
  • Success Rate
  • Real Questions
  • Updated Regularly
  • Portable Files
  • Unlimited Download
  • 100% Secured
  • Confidentiality: 100%
  • Success Guarantee: 100%
  • Any Hidden Cost: $0.00
  • Auto Recharge: No
  • Updates Intimation: by Email
  • Technical Support: Free
  • PDF Compatibility: Windows, Android, iOS, Linux
  • Test Engine Compatibility: Mac / Windows / Android / iOS / Linux

Premium PDF with 625 Q&A

Get Full Version

All ISEB Exams

ISEB Exams

Certification and Entry Test Exams

Complete exam list