Answer: B
QUESTION: 611
During which process would you obtain stakeholders' formal acceptance of the completed project scope?
1. Quality control
2. Scope verification
3. Scope control
4. Close project
Answer: B
QUESTION: 612
The initial development of a Project Scope Management plan uses which technique?
1. Alternatives identification
2. Scope decomposition
3. Expert judgment
4. Product analysis
Answer: C
QUESTION: 613
What is a hierarchically organized depiction of the identified project risks arranged by risk category?
1. Risk register
2. Risk breakdown structure (RBS)
3. Risk management plan
4. Risk category
Answer: B
QUESTION: 614
Which is a tool or technique used in scope definition?
1. Templates, forms and standards
2. Change requests
3. Stakeholder analysis
4. Project assumptions
Answer: C
QUESTION: 615
What is the total float of the critical path?
1. Can be any number
2. Zero or positive
3. Zero or negative
4. Depends on the calendar
Answer: C
QUESTION: 616
Which of the following is the correct network diagram for the table?
1. Begin - A - C - D - E - End - B - D
2. Begin - A - B - C - D - E - End
3. Begin - A - B - D - E - End A - C - D
4. Begin - A - C - D - E - End - B - C
Answer: A
QUESTION: 617
Which of the following is a schedule network analysis technique that takes limited resources into account?
1. Network reserve analysis
2. Critical chain method
3. Lead and lag adjustment
4. Critical path method
Answer: B
QUESTION: 618
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
1. The risk of achieving the shortened project time is increased.
2. The critical path will have positive total float.
3. Contingency reserves are released for redeployment by the project manager.
4. Duration buffers are added to maintain a focus on planned activity durations.
Answer: A
QUESTION: 619
Which estimating technique uses the actual costs of previous similar projects as a basis for estimating the costs of the current project?
1. Analogous
2. Parametric
3. Bottom-up
4. Top-down
Answer: A
QUESTION: 620
Your project has an EV of 100 work-days, an AC of 120 work-days, and a PV of 80 work-days. What should be your concern?
1. There is a cost under run.
2. There is a cost overrun.
3. May not meet deadline.
4. The project is 20 days behind schedule.
Answer: B
QUESTION: 621
Which illustrates the connection between work that needs to be done and its project team members?
1. Work breakdown structure
2. Network diagrams
3. Staffing management plan
4. Responsibility matrix
Answer: D
QUESTION: 622
When can pre-assignment of project team members occur?
1. When the project uses capital expenditures.
2. When the required staff can be acquired from outside sources.
3. When the project would be ignored due to travel expenses.
4. When the project is the result of specific people being promised as part of a competitive proposal.
Answer: D
QUESTION: 623
Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?
1. Risk identification
2. Qualitative risk analysis
3. Risk management planning
4. Quantitative risk analysis
Answer: B
QUESTION: 624
In which process might you use risk reassessment as a tool and technique?
1. Qualitative risk analysis
2. Risk monitoring and control
3. Monitor and control project work
4. Risk response planning
Answer: B
QUESTION: 625
A contract management plan is a subsidiary of what other type of plan?
1. Resource plan
2. Project management plan
3. Cost control plan
4. Expected monetary value plan
Answer: B

User: Dhruv*****

killexams.com played a crucial role in my success on the ISEB-PM1 exam. Although I failed the exam the first time around, their questions and answers exam practice tests were a game-changer for me. The materials were easy to understand, and even as a slow learner, I was able to keep up with the content. I passed the exam with an 89% score and felt elated. I would like to express my gratitude to Killexams for providing such an excellent resource for exam preparation.
User: Natalya*****

Whenever I want to pass my certification exam to keep my job, I immediately visit Killexams.com and search for the required certification test, purchase, and prepare for the exam. It is definitely worth admiring because I usually pass the test with excellent scores.
User: Zenya*****

I mostly used a mix of books to prepare for the exam. The questions in the Killexams.com material matched the exam questions accurately, which was incredibly helpful. I passed the exam with 89% marks about a month ago. Whoever tells you that ISEB-PM1 is too hard, do not believe them. The exam is tough, but using Killexams.com Questions and Answers and exam simulator as my sole source of preparation was the key to my success.
User: Liev*****

I had a positive experience with the preparation set provided by Killexams.com, which helped me achieve a score of over 98% in the iseb-pm1 exam. The questions are real and valid, and the exam simulator is an excellent tool for preparation. Even if you are not planning on taking the exam, this is a great learning tool for expanding your knowledge. I have recommended it to a friend who works in the same area but just received her CCNA.
User: Isla*****

Clearing the ISEB-PM1 exam seemed unrealistic to me at first because the test factors were honestly extreme. However, the Killexams.com exam guide illuminated my shortcomings, and I was able to correctly answer 90 out of 100 questions. The top-notch exam simulator helped me pass the ISEB-PM1 exam with ease. I offer my gratitude to Killexams.com for providing these wonderful services.

Features of iPass4sure ISEB-PM1 Exam

  • Files: PDF / Test Engine
  • Premium Access
  • Online Test Engine
  • Instant download Access
  • Comprehensive Q&A
  • Success Rate
  • Real Questions
  • Updated Regularly
  • Portable Files
  • Unlimited Download
  • 100% Secured
  • Confidentiality: 100%
  • Success Guarantee: 100%
  • Any Hidden Cost: $0.00
  • Auto Recharge: No
  • Updates Intimation: by Email
  • Technical Support: Free
  • PDF Compatibility: Windows, Android, iOS, Linux
  • Test Engine Compatibility: Mac / Windows / Android / iOS / Linux

Premium PDF with 625 Q&A