Certification Practice Test | PDF Questions | Actual Questions | Test Engine | Pass4Sure
ACP-620 : Managing Jira Cloud Projects Exam
Atlassian ACP-620 Questions & Answers
Full Version: 635 Q&A
Atlassian
ACP-620
Managing Jira Cloud Projects
https://killexams.com/pass4sure/exam-detail/ACP-620
Question: 44
Nash’s team just completed their first sprint.
What can they learn from this chart? (Choose three.)
(Assume Remaining Estimate and Time Spent is enabled for this board.)
A. Some of the issues are resolved during non-working days.
B. Some of the issues are still unresolved.
C. This sprint ends with 0 story points.
D. This sprint starts with 20 story points.
E. There are issues worth 5 story points resolved on July 13th.
F. There are no scope changes in this sprint.
Answer: C,E,F
Explanation:
The grey area indicates non-working days. There were no issues resolved during non-working days since story points
did not reduce in the grey area.
This chart starts drawing the Guideline and Remaining Values lines at the 18 story points on the y-axis.
On July 13th, story points were reduced from 15 to 10. This means that users have closed some issues that are worth 5
story points.
Users have closed all issues on July 20th. There are no story points remaining on this date.
Story points do not increase during this sprint. Since the Remaining Estimate and Time Spent is enabled for this board,
scope change is indicated in the Burndown Chart for the subtask.
Question: 45
A group of developers are working on multiple Jira projects. They can view all Jira projects and have the ‘Move
Issues’ permission in all Jira projects. However, they cannot move issues to some of the Jira projects.
What is the possible root cause of this problem?
A. They do not have the ‘View Issue’ permission in some projects.
B. They do not have the ‘Transition Issue’ permission in some projects.
C. They do not have the ‘Edit Issue’ permission in some projects.
D. They do not have the ‘Create Issue’ permission in some projects.
Answer: D
Explanation:
If users are moving issues from project to project, they need to make sure they have the Create Issues permission in
the Jira project they want to move it to.
Question: 46
Nash recently joined the team as a scrum master.
Which permission will allow Nash to perform the below actions? (Choose four.)
– Manage version
– Manage component
– Manage sprint
– Edit an issue’s due date
A. Administer Projects
B. Manage Sprints
C. Schedule Issues
D. Edit Issues
E. Manage Versions
F. Manage Components
Answer: A,B,C,D
Explanation:
Manage Versions and Manage Components do not exist in Jira project permissions.
Administer Projects permission allow users to administer a project in Jira, which includes managing versions and
components.
Manage Sprints permission allow users to manage sprints. Users require Edit Issues and Schedule Issues permissions
to edit the issues’ due date.
Question: 47
Which of the following are suitable scenarios to use Jira group? (Choose four.)
A. Members of the group are responsible for making bulk changes on multiple issues.
B. The project administrator will manage group membership.
C. Same users will be working on multiple projects.
D. Permission can be managed at the global level.
E. The site administrator will manage group membership.
F. Team members require ‘Work On Issues’ permission to log work done.
Answer: A,B,C,D
Explanation:
Work on Issues permission is not a global permission, but it is a project-level permission. Thus, it can be managed at
the project level by the project administrator and does not require a group.
Group:
– Only site administrators have access to create groups and assign users to the group.
– Groups can be associated with global and project permissions.
– Groups can be used in multiple Jira projects.
Role:
– Project administrators can manage roles’ membership.
– Only Jira administrators can create a new role.
– Roles are associated with project permissions.
– Each Jira project has default roles.
– Users and groups can be assigned roles.
Question: 48
Nash is creating a new Scrum board with multiple Jira projects. Each project has a different status in its workflow.
Which of the following are true? (Choose two.)
A. Some issues will be hidden from the board.
B. The user cannot create a new board with multiple Jira projects.
C. All statuses will be mapped to 3 default columns: To Do, In Progress, and Done
D. All issues will be hidden from thewwwboard.dumpspanda..com
E. The status will be mapped to the first selected project when creating the new board.
Answer: C,D
Explanation:
If users are creating a new board (Kanban or Scrum) with multiple Jira projects, and each project has a unique
workflow, all statuses will be mapped to 3 default columns: To Do, In Progress, and Done.
On the Kanban board, the issues will appear on the board as soon as users create the board.
On the Scrum board, all issues will not appear on the board because only issues in the active sprint will appear on the
Scrum board. After creating a new Scrum board, you do not have an active sprint.
Question: 49
Which of the following are false about the roadmap? (Choose three.)
A. Users can choose which epics they want to display on the dashboard. Either Complete or Incomplete.
B. Users can change the view setting to customize their roadmap’s view. The changes will apply to all users that have
access to that project.
C. Schedule bars for child issues are currently available for scrum teams only.
D. Users can customize epic’s color directly from the roadmap.
E. Users can change the epic bar timeline to weeks, months, quarters, or yearly.
Answer: A,B,E
Explanation:
View Settings is a collection of settings that allow users to adjust their personal view of the roadmap. The settings only
apply to individual users. Users can change their view at any time.
Schedule Bars for child issues are currently available for scrum teams only.
Epic Display Options allow users to use the dropdown to select which epics to display. The current options are All,
Incomplete, or Complete.
Users can adjust the color of an epic directly on the roadmap. Simply right-click the epic and choose a fresh color.
The epic bar has a default duration according to how users view their timeline. The default durations are weeks,
months, or quarters.
Question: 50
Which of the following can be explained from the chart below?
A. Users have not started the sprint yet.
B. Users deleted the sprint.
C. Users closed some issues the moment the sprint started.
D. There are no issues in the sprint.
Answer: C
Explanation:
If the grey ‘guideline’ line does not show, the sprint may have been started before any issues were assigned to it.
In this case, since the grey ‘guideline’ line does show up in the chart, the sprint already started. The ‘remaining values’
line indicates that someone closed some issues that are worth 5 story points as soon as they started their sprint.
For More exams visit https://killexams.com/vendors-exam-list
User: Rubal***** Preparing for the acp-620 exam was a pleasant experience for me, and thanks to Killexams.com Questions and Answers, I have found a way to pass all the further stages easily. Their extensive questions and answers made it easy for me to plan my study schedule even with limited time. The assistance from Killexams was invaluable in my exam preparation. |
User: Lenin***** I express my sincere gratitude to killexams.com practice tests for helping me pass the ACP-620 exam with 91% marks. It was their questions and answers that helped me achieve this feat in just 12 days of preparation. I could not have imagined it three weeks before the test until I discovered their product. Thank you so much for your valuable help, and I wish all the best to your team members for their future endeavors. |
User: Stephen***** I purchased a brain dump test for the ACP-620 exam from killexams.com and was worried about its usefulness after hearing about the update. However, their customer support staff informed me that the exam had been recently updated, and upon testing it against the latest objectives, I found that it was indeed updated. I am impressed with their efficiency and customer service, and I am now looking forward to taking my ACP-620 exam in two weeks. |
User: Melanie***** killexams.com provides splendid exam preparation resources for the ACP-620 exam. I purchased their material because I could not find any reliable books or PDFs to study from. Their practice exams provided real questions that accurately reflected the exam format, with no irrelevant or unnecessary information. I highly recommend killexams.com to anyone taking the ACP-620 exam. |
User: Shura***** Thanks to the questions and answers provided by killexams.com, I passed my acp-620 exam with 80%. The practice papers with answers were extremely useful in helping me understand the concepts, and I am grateful for their help. |
Features of iPass4sure ACP-620 Exam
- Files: PDF / Test Engine
- Premium Access
- Online Test Engine
- Instant download Access
- Comprehensive Q&A
- Success Rate
- Real Questions
- Updated Regularly
- Portable Files
- Unlimited Download
- 100% Secured
- Confidentiality: 100%
- Success Guarantee: 100%
- Any Hidden Cost: $0.00
- Auto Recharge: No
- Updates Intimation: by Email
- Technical Support: Free
- PDF Compatibility: Windows, Android, iOS, Linux
- Test Engine Compatibility: Mac / Windows / Android / iOS / Linux
Premium PDF with 635 Q&A
Get Full VersionAll Atlassian Exams
Atlassian ExamsCertification and Entry Test Exams
Complete exam list